26 August 2009

Day 19 - the cellar is finished

Today we finished the final course of the cellar walls, eleven working days after starting the blockwork (some of the days were very long and some were short). We even had time to clear out all of the extra blocks to be used for the perimeter piers, and cleaned the base of the cellar.



Each of the 5 chambers of the cellar has at least two ventilation windows, one at the top of each side wall. We also left a hole for the services to come into the each of the cellars below grade.

The bunker!