Today was another slow day, frustrated by weather and waiting for material delivery.
The plywood for the ground floor structure and the roof arrived, much more plywood than I thought we would use, but it is providing the main stabilizing structure for the house.
With all the rain and wind we have been gettign lately, We made sure it was wrapped up tight.
We cut and bent the rebar that will tie the piers to the footings, and tied them into position. Apart from the bolts and bearing plate for the main walls of the cellar, we are now ready for the next load of concrete.
01 September 2009
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment