Day 48 - floor slab finished, varnished and covered

We finished all of the remaining small pieces of the flooring, and now the structural slab is complete.

We decided to varnish the surface of the OSB board in order to protect it in case some water came through the plastic. Also, there is a good chance that we will move in to the houses before they are finished, before the final hardwood flooring is in place, and the varnished OSB board will be a better floor in the interim.




We covered the entire floor slab surface with two sheets of silage cover, reusing the old one and adding a new one on top.


We hope that this plastic will last until the roof is in place and plan to place the wall panels directly on top of the plastic. So we secured the edges with batons and covered the surface with pallets and sheets of wood to prevent the plastic from billowing up too much in the wind.